Jim & Jodi's House - Estimated Schedule

DATEEVENT
9/9/04Ceilings painted
9/10/04 & 9/13/04Install wood floor
9/13/04Millwork delivery
9/14/04Cabinet install
9/20/04Stain & paint start
9/28/04Tile & laminate tops (goes until 10/6 or so)
9/28/04Garage doors might be hung near this time
10/7/04 & 10/8/04Wood floor finish
10/11/04Appliance delivery (bring door knobs out!)
10/11/04 & 10/14/04Trade finish (plumbers & electricians)
10/12/04 & 10/13/04Trimming finish (door knobs)
10/14/04Clean for carpet
10/15/04 & 10/18/04Carpet delivered & installed
10/19/04Drywall touchup
10/20/04 & 10/21/04Paint touchup
10/22/04Clean house
10/25/04Home walkthrough
11/1/04Tentative close date