DATE | EVENT |
9/9/04 | Ceilings painted |
9/10/04 & 9/13/04 | Install wood floor |
9/13/04 | Millwork delivery |
9/14/04 | Cabinet install |
9/20/04 | Stain & paint start |
9/28/04 | Tile & laminate tops (goes until 10/6 or so) |
9/28/04 | Garage doors might be hung near this time |
10/7/04 & 10/8/04 | Wood floor finish |
10/11/04 | Appliance delivery (bring door knobs out!) |
10/11/04 & 10/14/04 | Trade finish (plumbers & electricians) |
10/12/04 & 10/13/04 | Trimming finish (door knobs) |
10/14/04 | Clean for carpet |
10/15/04 & 10/18/04 | Carpet delivered & installed |
10/19/04 | Drywall touchup |
10/20/04 & 10/21/04 | Paint touchup |
10/22/04 | Clean house |
10/25/04 | Home walkthrough |
11/1/04 | Tentative close date |