Jim & Jodi's House


FloorPlans

First draft - April 16, 2004
Second draft - May 5, 2004
Third draft - May 13, 2004
Fourth draft - May 18, 2004
Fifth draft - May 18, 2004
Sixth draft - June 23, 2004

Other Items

The schedule - Estimated schedule for the rest of the work on the house.
Low Voltage (Network, Telephone, & cable TV) - July 4, 2004
Kitchen Cabinets - June 18, 2004
Site Survey - June 2, 2004
Garage Options - May 12, 2004

Construction Pictures

June, 2004
24th - Foundation forms being assembled
27th - Foundation poured and forms off, but backfilling not done yet

July, 2004
2nd - Backfilling done and lot smoothed and shaped around the foundation and basement walls
8th - Framing underway. Outside basement walls up and work started on first floor.
9th - Framing underway. Outside walls on first floor up.
15th - Framing underway. 2nd floor joists, 2nd floor subfloor, and one truss up..
17th - Second floor joists all in and 2nd floor walls started.
20th - Second floor almost completely framed and garage almost framed. Nearly ready for trusses.
24th - The roof is going up!
31st - The exterior of the house nearly completed

August, 2004
23rd - Inside drywall up, running phone, cable, & TV.

September, 2004
1st - Taping and mudding well underway
14th - Taping done, ceilings textured & painted, garage drywalled, hardwood floors installed, cabinet installation begun
30th - Trim up & stained, painting begun. Siding on the back of the house almost completed.

October, 2004
7th - Painting, staining, tile work, & bathroom counters all done.
20th - Kitchen counters in, most appliances installed, and many lights working.

Last modified on October 21, 2004
This page maintained by Jim Lowell - jlowell@visi.com